# Adding Recommendations & Actions

Recommendations (called Reviews in some modules) and actions keep the follow-up for a record in one place. Each recommendation can have several actions, and each action can have progress updates and comments.

Actions are timestamped when they are created or changed, assignees can be sent reminder emails when they are overdue, and several users can work on the same action.

**Note:** **Applies to:** record owners and managers. Assignees can add progress updates to their own actions. The steps below use an Audit Tracker issue, but the same section appears in other modules.

## Adding a Recommendation

1. Open the record, select the **Recommendations & Actions** tab, then click **Add Recommendations**.

![The Add Recommendations link on the Recommendations & Actions tab](https://support.symbiant.co.uk/wp-content/uploads/2026/10/creating-an-audit-issue-08-add-rec.png)

1. Enter the **Recommendation Details**. **Recommendation By** and **Date Added** are filled in when you save.

![Recommendation Details filled in](https://support.symbiant.co.uk/wp-content/uploads/2026/10/creating-an-audit-issue-09-rec.png)

## Adding an Action

1. Click **Add Actions** below the recommendation, then enter the **Action Details**.
2. Choose the **Assignees**, set a **Due Date**, and tick **Implemented** once the action is complete. The status at the right changes from **Not Started** to **In-Progress** and then **Complete**.

![Action Details with Assignees, Due Date and Implemented highlighted](https://support.symbiant.co.uk/wp-content/uploads/2026/10/creating-an-audit-issue-10-action.png)

## Adding a Progress Update

1. Click **Add Action Progress Update** under the action.

![The Add Action Progress Update link under an action](https://support.symbiant.co.uk/wp-content/uploads/2026/10/adding-recommendations-actions-04-progress.png)

1. Enter the **Progress Update**. Tick **Completed** if this update finishes the work.
2. To attach supporting documents, click the **+** icon on the **Attachments** section.

![A progress update with the Completed button and the Attachments + icon highlighted](https://support.symbiant.co.uk/wp-content/uploads/2026/10/adding-recommendations-actions-05-update.png)

## Commenting on a Progress Update

1. Click **Add Progress Update Comments** under the update, then enter a **Comment Response**. This is a good way to give feedback on an update.

![A comment response added to a progress update](https://support.symbiant.co.uk/wp-content/uploads/2026/10/adding-recommendations-actions-06-comment.png)

## Saving

1. Click **Save** to save and close, or the pencil icon beside it to save and keep editing.

![The Save and Save and Edit buttons at the top right](https://support.symbiant.co.uk/wp-content/uploads/2026/10/creating-an-audit-issue-11-save.png)

## Removing a Recommendation or Action

1. Click the **minus** icon at the top right of the Recommendations or Actions section. You may not see it if your role cannot remove them.

![The minus icon on the Actions section](https://support.symbiant.co.uk/wp-content/uploads/2026/10/adding-recommendations-actions-08-minus.png)

1. A bin icon appears over each item. Click the bin on the one you want to remove.

![The bin icon shown over an action](https://support.symbiant.co.uk/wp-content/uploads/2026/10/adding-recommendations-actions-09-bin.png)

1. Click **Save** to confirm. To keep the item after all, click **Cancel** instead.

**Note:** Actions, progress updates and comments are nested inside their recommendation, so removing a recommendation removes everything inside it when you save.