# Approving and Validating Tracker Findings

A finding on a Monitoring Action Tracker moves from being raised to being fully closed. Along the way you record when it is due and when it was completed, any extension request, whether the recommendation was accepted, who validated the fix and who gave final approval. This article explains each of those fields.

**Note:** **Applies to:** users who can edit the tracker. Your organisation decides who validates and approves findings; Symbiant records who did it and when.

## Opening the Finding

1. Select **Monitoring Action Tracker** in the left menu.

![Monitoring Action Tracker selected in the left menu](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-01-menu.png)

1. Click the tracker in the **All Trackers** grid and scroll down to the finding.

![A tracker highlighted in the All Trackers grid](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-02-record-v2.png)

## The Typical Lifecycle

- The owner works on the finding, recording **Recommendations** and **Actions** inside it.
- When the work is finished, the **Date Completed** is entered and the **Finding Status** updated.
- If more time is needed, an **Extension Request** is recorded.
- The reviewer ticks **Accepted** and records who validated the fix and when.
- Final **approval** closes the finding.

**Note:** The order and the people involved depend on your own process. The fields below are all optional, so use the ones that fit how you work.

## Target Date and Date Completed

1. The **Target Date** is when the finding should be resolved by (for example, a change to the supplier set-up process by 30 Nov 2026).
2. The **Date Completed** is the date the work was actually finished. Aim for a date on or before the target date.

![The Target Date and Date Completed fields on a finding](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-03-dates.png)

## Requesting an Extension

1. Tick **Extension Request** if the target date can't be met. An **Extension List** box appears.
2. Record the new date asked for and the reason in **Extension List**.

![Extension Request ticked, with the Extension List box filled in](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-04-extension.png)

## Accepting and Validating

1. Tick **Accepted** once the reviewer accepts the finding's recommendations or the work done. Two validation fields appear.

![The Accepted tick box, with the validation fields shown below it](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-05-accepted.png)

1. Select who validated the finding in **Validated By Select** and pick the **Date Validated**. Validation usually happens after the Date Completed.

![Validated By Select set to Dev Account and Date Validated 19 Oct 2026](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-06-validation.png)

## Approving the Finding

1. Once the finding is validated and any extension is resolved, select the approver in **Approved By** and pick the **Approved Date**. An approved finding is fully complete.

![Approved By set to Dev Account and Approved Date 20 Oct 2026](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-07-approval.png)

## Adding Recommendations and Actions

Each finding has its own **Recommendations** section, which works like [Reviews & Actions](https://support.symbiant.co.uk/kb/reviews-actions/) on other records.

1. Click **Add Recommendations** and enter the recommendation. Recommendation By and Recommendation Date fill in when you save.
2. Inside the recommendation, click **Add Actions**. Enter the action **Details**, choose the **Assignees** and set a **Due Date**. Tick **Implemented** when the action is done.
3. Assignees can record progress with **Add Action Progress Update**.

![A recommendation with one action: details, assignee Dev Account, due date 30 Nov 2026, and the Add Action Progress Update button](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-08-recommendations.png)

## Saving

1. Click **Save** to save and close, or the pencil icon (**Save and Edit**) to save and stay on the tracker.

![The Save and Save and Edit buttons at the top right](https://support.symbiant.co.uk/wp-content/uploads/2026/10/approving-and-validating-tracker-findings-09-save.png)

## Related Articles

- [Adding Tracker Findings](https://support.symbiant.co.uk/kb/adding-tracker-findings/)
- [Reviews & Actions](https://support.symbiant.co.uk/kb/reviews-actions/)
- [Generating a Tracker Action Report](https://support.symbiant.co.uk/kb/generating-a-tracker-action-report/)