description: "Importing risks works like any other import, with three extra things to get right: the **Register**, the **Score Set** and the **scores**. This article covers those. For the basic steps, see [Importing Data (Generic)](https://support.symbiant.co.uk/kb/importing-data-generic/). **Note:** **Applies to:** users whose role…"
url: "https://support.symbiant.co.uk/kb/importing-data-risk-register-specific/"
updated: "2026-10-30"
category: Importing Data
tags:
  - Add
  - Import
---

# Importing Data (Risk Register Specific)

Importing risks works like any other import, with three extra things to get right: the **Register**, the **Score Set** and the **scores**. This article covers those. For the basic steps, see [Importing Data (Generic)](https://support.symbiant.co.uk/kb/importing-data-generic/).

**Note:** **Applies to:** users whose role includes **Import...** in the Register Risks ⋮ menu (usually admins and risk managers).

## Before You Start

Check your file follows the rules in [Preparing Data for Import (Risks)](https://support.symbiant.co.uk/kb/preparing-data-for-import-risks/).

## Choosing the File

1. Open **Register Risks**.
2. Click the three dots (⋮) at the top right, then **Import...**.
3. Click **Choose File** and pick your CSV file.
4. Turn on the translate button (next to the star) so the field names are easy to read.

## Required Fields

Match your reference column to **Reference** and your title column to **Summary**. These two are always required. Also import any other fields that are required on your risk form (marked with a red asterisk).

## Register

Always import a **Register**. Without one, the risks are only stored in the Risk Universe and don't appear in your registers.

1. Under the register column, choose **Register**.
2. In the second drop-down that appears, choose **Register** again so the value is imported as text.

If a register in your file doesn't exist yet, it is created during the import. It appears in Register Risks > **Register** with no colour or sort order, so set those afterwards. Check the spelling first: a typo creates an extra register. Other drop-down fields work the same way.

## Score Set

**Critical:** Always import a **Score Set**, so the risks can be scored as soon as they are imported.

1. Under the score set column, choose **Score Set**.
2. In the second drop-down, choose **Set Name**.

Every system comes with a **Normal** score set. You can import all risks against Normal and change it later. A score set name that doesn't exist yet is created during the import, but it will be empty and need setting up before it works.

## Scores

Scores are optional. You only need to import the **Impact** and **Likelihood** values, not the total, because Symbiant calculates the total from the score set.

1. Under each score column, choose the score: **Inherent Score**, **Residual Score** or **Target Score**.
2. In the second drop-down, choose **Impact** or **Likelihood**.

Use the numbers from your score set (for example Impact 4, Likelihood 3).

![Register, Score Set and score columns matched](https://support.symbiant.co.uk/wp-content/uploads/2026/10/importing-data-risk-register-specific-01-rimp-mapped.png)

## Saving the Layout as a Preset

1. Click the star at the top right of the import screen, then **Save preset...**.

![The preset menu](https://support.symbiant.co.uk/wp-content/uploads/2026/10/importing-data-risk-register-specific-02-imp-star.png)

1. Enter a name and click **Save**. Next time, use **Load preset...** to apply the same choices.

## Checking and Importing

1. Click **Continue** and check the **Review CSV Import** screen.

![Reviewing the risks before import](https://support.symbiant.co.uk/wp-content/uploads/2026/10/importing-data-risk-register-specific-03-rimp-review.png)

1. Click **Import**. The risks appear in **Register Risks**, scored and in their registers.

**Critical:** References must be unique. If an imported reference already exists, the existing risk is **overwritten** with the imported version.